Equipment schedule tool

Food truck equipment payload and counter-space calculator

Turn manufacturer equipment data into a preliminary weight and space schedule. Track payload remaining, counter run, floor footprint and missing specifications before the builder freezes the layout.

Build the schedule
Use verified source data: this calculator does not provide generic equipment weights. Enter manufacturer dimensions and masses, then have the completed vehicle weighed and checked for axle, tire, structural and stability limits by qualified specialists.
Step 1

Set the available allowances

Use available payload for the intended base vehicle or trailer—not gross vehicle rating by itself. Put all planned non-equipment load into one allowance and avoid double counting.

Step 2

Add manufacturer equipment data

For each item, enter quantity, unit weight and full installed width/depth. Choose counter-mounted, floor-standing or overhead/other so the correct space totals are used.

EquipmentLocationQtyUnit weightInstalled widthInstalled depth

Payload is not gross vehicle rating

Confirm what the chassis, body, trailer and fixed conversion already weigh. Available payload is the verified capacity left for the build elements and operating load you intend to add.

Full tanks matter

Water, wastewater, fuel, gas, batteries and stock can materially change loaded mass and axle reactions. Model the worst intended operating condition and do not count an allowance twice.

Installed width is more than cabinet width

Include required clearances, guards and the movement of doors or drawers when the occupied counter run is affected. Confirm maintenance access separately in the layout plan.

Final verification

Before fabrication or road use

  • Reconcile every schedule item against manufacturer documents and the builder quotation.
  • Confirm whether stands, accessories, liquids and mounting hardware are included in stated weights.
  • Check axle, tire, coupling and towing limits—not only total payload.
  • Coordinate equipment position with water tanks, batteries, generators, gas cylinders and stored product.
  • Verify counters, clearances, egress, ventilation, fire protection and utility access in the final drawings.
  • Obtain completed and loaded vehicle weights on appropriate scales.